2026 C L C 377
2026 C L C 377
[Sindh]
Before Muhammad Iqbal Kalhoro and Mohammad Abdur Rahman,
JJ
Messrs VISIONARY BALUCHISTAN MEDIA CORPORATION ---
Appellant
Versus
Mst. SHAHNAZ ABID and 2 others ---Respondents
High Court Appeal No. 374 and C.M.A. No. 3663 of 2022, decided on 7th
October, 2025.
(a) Specific Relief Act (I of 1877)---
----Ss.12 & 22---Contract Act (IX of 1872), S.55---Limitation Act (IX of
1908), First Sched., Art.113---Civil Procedure Code (V of 1908), O.VII,
R.11---Suit for specific performance of agreement to sell filed after a
seven years delay---Time being essence of contract---Principle---
Discretionary relief, granting of---Scope---Failure to deposit balance
sale consideration at institution of suit---Impact on entitlement to
relief stated---Brief facts were that the appellant (vendee) and
respondent (vendor) entered into a sale agreement regarding suit
property, under which only Rs.14,00,000/- of the agreed Rs.19 million
sale consideration was paid, and the balance was required to be
cleared under a compromise order stipulating payment by
07.07.2013---The appellant neither complied with the compromise
terms nor made any further payment, and after several years filed
suit for specific performance, which was rejected under O.VII R.11,
C.P.C. as barred by limitation---The issue before the High Court was
whether the appellant s suit for specific performance which was
filed years after the agreed timelines and without payment of the
remaining consideration, was maintainable in law and within
limitation, so as to justify interference with the rejection of plaint
and denial of discretionary relief? ---Held: Nothing by the appellant
was articulated to explain such inordinate delay, let alone making
efforts to make payment of remaining sale consideration in time---
Single Judge had taken into account the fact that the contract
between the parties was more than a decade old and worth of the
subject property had meanwhile increased manifold; hence, such
development i.e. property getting hugely costly was sufficient to
deny the discretionary relief to the appellant---On the point of
limitation, it had been held by the Single Judge that the sale
agreement was executed on 19.04.2012 and the plaint was presented on 09.11.2019 after seven years, whereas, under Art.113 of the
Limitation Act, appellant had only three years to file suit for seeking
enforcement of the contract from the date of refusal---Not only the
suit was barred by time but because of failure of the appellant to
adhere to the terms and conditions mentioned in the compromise
order he had made himself disentitled to seek discretionary relief of
specific performance by the respondent---Further, due to failure of
appellant to deposit the remaining sale consideration in the Court at
the time of instituting the suit, the case of the appellant seeking
relief of specific performance got on weaker footings from the very
inception---In the present case, relevant material showing genuine
efforts of the appellant to adhere to his part of the agreement was
lacking---Further, no justification had been articulated to warrant in
action of the appellant to file the suit within time firstly, and
secondly his failure to deposit the remaining sale consideration
within time in the Court even---The plaint had been rightly rejected
under O.VII, R.11 of C.P.C.---No illegality or error in the impugned
order to justify its reversal was found---Present appeal was without
any merit and was dismissed.
(b) Specific Relief Act (I of 1877)---
----Ss.12 & 22---Contract Act (IX of 1872), S.55---Time being essence of
contract---Principle---Scope---When the time is essence of the
agreement, its violation will render the defaulting party disentitled
to Court s interference in the shape of discretionary relief.
(c) Specific Relief Act (I of 1877)---
----Ss.12 & 22---Specific performance of agreement to sell---
Discretionary relief, grant of---Scope---The discretionary relief can
be extended to a person whose actions are anchored in bona fide
while pursuing a contract, and he is seen to be making genuine
efforts to perform his part of the agreement---Anyone whose action
speaks otherwise will not be held entitled to such a relief.
Anwar Hussain for Appellant.
Khalil Ahmed for Respondent No. 1.
Date of hearing: 7th October, 2025.
JUDGMENT
MUHAMMAD IQBAL KALHORO, J.---This appeal is filed against an
order dated 06.09.2022 rejecting the plaint under Order VII Rule 11,
C.P.C. and decree dated 19.09.2022 in Suit No.852/2021. 2. Record reflects that appellant filed the aforesaid suit, whereas,
respondent No. 1 filed Suit No.1228/2017. It was stated, a sale
agreement was executed on 19.04.2012 between the parties in respect
of property i.e. Plot No.5-F, admeasuring 400 square yards, situated at
Block-6, PECHS, Karachi. The said sale agreement gave way to
compromise between the parties in Suit No.1701/2009, decided
through an order dated 07.11.2012 stipulating that entire balance sale
consideration should be paid to respondent No. 1 on or before
07.07.2013.
3. The record further reflects that in terms of the sale agreement,
the sale consideration of the property was fixed as Rs.19 Million
(Rupees Nineteen Million), out of which, only Rs.14,00,000/- were paid
to the vendor/defendant/respondent No. 1 by appellant. In the
agreement, the sale consideration was stipulated to be paid before a
certain time but the appellant failed to adhere to the conditions and
defaulted. The ground to justify the default by the appellant was that
respondent No. 1 had no clear title over the property and that the
remaining payment was subject to the clearance of title. When the
compromise in Suit No.1701/2009 could not be given effect to by the
parties, the appellant filed Suit No.852/2021 for specific performance
of contract. This suit was resisted by respondent No.1 on various
grounds and in addition an application under Order VII Rule 11, C.P.C.
was filed for rejection of the plaint, which through the impugned
order has been allowed. The plaint in Suit No.852/2021 has been
rejected, whereas, Suit No.1228/2017 in view of such fact has been
dismissed as withdrawn.
4. We have heard the parties. Learned counsel for appellant has
admitted that the only payment made by appellant towards the sale
consideration amounting to Rs.14,00,000/- was made in the year 2012
in terms of agreement dated 19.04.2012. Thereafter, not a single penny
towards sale consideration has been paid by the appellant despite
filing of the suit for specific performance of contract. It is not even
disputed that meanwhile the price of the subject property has
increased manifold. It is not disputed either that the relief of specific
performance is discretionary which the Court can deny even in
presence of positive evidence in favour of vendee, when the Court is
satisfied that such relief is not equitable.
5. Learned single Judge has observed in clear terms in the impugned
order that the order passed in earlier suit (Suit No.1701/2009)
stipulating compromise between the parties and payment of
remaining sale consideration on or before 07.07.2013 had not been
complied with even partly by the appellant. Nothing by the appellant
has been articulated to even explain such inordinate delay, let alone making efforts to make payment of remaining sale consideration in
time. It has also been held by learned single Judge that proviso in the
contract stipulating fixed time for making payment of remaining sale
consideration has made the time essence of the agreement. When the
time is essence of the agreement, its violation will render the
defaulting party disentitled to Court s interference in the shape of
discretionary relief.
6. The impugned order further shows that against the appellant rent
proceedings were initiated by the respondent earlier, in which, the
tentative rent order was passed and appellant was directed to make
good of certain amount towards the rent but he failed to comply with
the same even though ultimately he was directed to do so by the
Supreme Court. While noting such facts, the learned single Judge has
also taken into account the fact that the contract between the parties
was more than a decade old and worth of the subject property has
meanwhile increased manifold; hence, in his view, even such
development i.e. property getting hugely costly was sufficient to deny
the discretionary relief to the appellant.
7. On the point of limitation, it has been held by learned single Judge
that the sale agreement was executed on 19.04.2012 and the plaint was
presented on 09.11.2019 after seven years, whereas, under Article 113
of the Limitation Act, appellant had only three years to file suit for
seeking enforcement of the contract from the date of refusal. The
earlier contract dated 19.04.2012 was novated by the order dated
07.11.2012 disposing of the Suit No.1701/2009 on the basis of
compromise, in which, appellant was directed to make good of the
remaining sale consideration before a certain date (07.07.2013), but
even that appellant failed to comply with.
8. In consideration of all these relevant facts, the learned single
Judge has held that the suit of the appellant is hit by Article 113 of the
Limitation Act and is apparently barred by time. In lengthy arguments
rendered by learned counsel for appellant, he has been unable to
present any material scuttling the findings made by learned single
Judge in the impugned order. Not only the suit was barred by time but
because of failure of the appellant to adhere to the terms and
conditions mentioned in the order dated 07.11.2012, he has made
himself disentitled to discretionary relief of specific performance by
the respondent.
9. Further, due to failure of appellant to deposit the remaining sale
consideration in the Court at the time of instituting the suit, the case of
the appellant seeking relief of specific performance got on weaker
footings from the very inception. The discretionary relief can be
extended to a person whose actions are anchored in bona fide while pursuing a contract, and he is seen to be making genuine efforts to
perform his part of the agreement. Anyone whose action speaks
otherwise will not be held entitled to such a relief. In the present case,
relevant material showing genuine efforts of the appellant to adhere
to his part of the agreement is lacking. Further, before us no
justification has been articulated to warrant inaction of the appellant
to file the suit within time firstly, and secondly his failure to deposit
the remaining sale consideration within time in the Court even. The
plaint has been rightly rejected under Order VII Rule 11, C.P.C.; hence,
we do not find any illegality or error in the impugned order to justify
its reversal in this appeal. Consequently, we find this appeal to be
without any merit, and accordingly dismiss it along with pending
application.
The appeal is disposed of.
UN/V-1/Sindh Appeal dismissed.

Comments
Post a Comment